A small project consists of 3 activates P, Q and R to be executed in that sequence. The relationship between Time Duration (in ‘Units’ of time – T) and corresponding total direct cost (C units) for each of the activities, for alternate mutually exclusive possible durations for each activity, are tabulated herewith:
|
P |
|
Q |
|
R |
|
|
T |
C |
T |
C |
T |
C |
|
8 |
250 |
6 |
340 |
8 |
400 |
|
9 |
235 |
7 |
320 |
10 |
375 |
|
10 |
225 |
8 |
295 |
12 |
350 |
|
11 |
215 |
9 |
275 |
|
1
965 units
2
950 units
3
940 units
4
925 units