The following details pertain to the crossing of a canal with a natural drain.

Full supply level in canal = RL 213.5 m

Bed level of canal = RL 212 m

High flood level in drain = RL 210 m

Considering the given details, which type of cross drainage work is best suited to the site?

1
Aqueduct
2
Super passage
3
Syphon aqueduct
4
Syphon