An activity in CPM netbook has duration of 4 days. The free float for activity is 10 days and total float is 12 days. Find the difference in latest start time and earliest start time of successor event.

Enter numerical value using the virtual keypad. Round off where necessary.

Sponsored

hivanix.in

Visit

This quiz is brought to you by hivanix.in

🌐 Web App Development

Quick Navigation