For the network shown below, what is the optimum duration and optimum cost
Indirect cost on the project = Rs. 105 /day
|
Activity |
Normal time |
Cost time |
Normal cost |
Crash cost |
|
1 - 2 |
6 |
3 |
500 |
650 |
|
2 - 3 |
7 |
4 |
250 |
350 |
|
2 - 4 |
3 |
`1 |
350 |
525 |
|
3 - 4 |
5 |
3 |
700 |
950 |
1
12 hour and 3310/-
2
12 days and 3310 /-
3
10 days and 3000 /-
4
10 days and 3310 /-