For the following data, what will be the expected project completion time?
|
Activity |
Predecessor |
T0 |
Tm |
Tp |
|
A |
- |
2 |
5 |
8 |
|
B |
A |
6 |
10 |
20 |
|
C |
A |
1 |
3 |
5 |
|
D |
B |
4 |
5 |
12 |
|
E |
C |
6 |
8 |
10 |
|
F |
C |
4 |
9 |
14 |
|
G |
E |
6 |
7 |
8 |
|
H |
D |
4 |
6 |
7 |
|
I |
F |
5 |
8 |
10 |