For the following data, what will be the expected project completion time?

Activity

Predecessor

T0

Tm

Tp

A

-

2

5

8

B

A

6

10

20

C

A

1

3

5

D

B

4

5

12

E

C

6

8

10

F

C

4

9

14

G

E

6

7

8

H

D

4

6

7

I

F

5

8

10

Enter numerical value using the virtual keypad. Round off where necessary.