Which of the following do not characterize the critical path?
1. Falls on a single straight line between start and end nodes
2. Has no dummies
3. Indicates the minimum feasible duration for the complete project
4. Indicates the maximum sensible duration in which to complete the project
5. Has no parallel sub-paths between any two nodes on it.
1
2, 4 and 5
2
1, 2 and 5
3
2, 3 and 4
4
1, 3 and 4