The optimistic, most likely and pessimistic time estimates of activity are 8, 15 and 18 weeks respectively. The Probable range of completion time of the activity will be
1
5.99 to 22.67 weeks
2
8.54 to 18.59 weeks
3
9.32 to 19.34 weeks
4
10.20 to 20.31 weeks