engineering recuitment GATE CE 2023-24 Test Series Construction Materials and Management Project Planning CPM
A two activity network data is given by the table. The project overhead costs are Rs. 400 per day. The least cost plan for the network is
|
Activity |
Normal duration |
Normal cost |
Crashing duration |
Crash cost |
|
1 - 2 |
6 |
7000 |
4 |
9000 |
|
2 - 3 |
10 |
9000 |
5 |
13000 |
1
22,400 /-
2
23,400 /-
3
36,000 /-
4
24,000 /-