For the following activities and duration, The expected time of completion is _______ days
|
Activity |
Predecessor |
Duration (in weeks) |
||
|
|
|
Optimistic |
Most likely |
Pessimistic |
|
A |
- |
5 |
6 |
7 |
|
B |
- |
1 |
3 |
5 |
|
C |
- |
1 |
4 |
7 |
|
D |
A |
1 |
2 |
3 |
|
E |
B |
1 |
2 |
9 |
|
F |
C |
1 |
5 |
9 |
|
G |
C |
2 |
2 |
8 |
|
H |
E, F |
4 |
4 |
10 |
|
I |
D |
2 |
5 |
8 |
|
J |
H, G |
2 |
2 |
8 |
Enter numerical value using the virtual keypad. Round off where necessary.