For the following activities and duration, The expected time of completion is _______ days

Activity

Predecessor

Duration (in weeks)

 

 

Optimistic

Most likely

Pessimistic

A

-

5

6

7

B

-

1

3

5

C

-

1

4

7

D

A

1

2

3

E

B

1

2

9

F

C

1

5

9

G

C

2

2

8

H

E, F

4

4

10

I

D

2

5

8

J

H, G

2

2

8

Enter numerical value using the virtual keypad. Round off where necessary.