For the following detail of the network, which of the following activity should be crashed first?

Activity

Normal duration (weeks)

Normal cost (Rs.)

Crash duration (weeks)

Crash cost (Rs.)

1 - 2

4

4000

2

12000

2 - 3

5

3000

2

7500

2 - 4

7

3600

5

6000

3 - 4

4

5000

2

10000

1
1 - 2
2
2 - 3
3
2 - 4
4
3 - 4