engineering recuitment BHEL Engineer Trainee Mock Test 2025 Industrial Engineering Operations Research PERT and CPM
. A project consists of following activities:
|
Activity |
Predecessor |
Estimated duration (in days) |
||
|
Optimistic |
Most-likely |
Pessimistic |
||
|
A |
- |
1 |
1 |
7 |
|
B |
- |
1 |
4 |
7 |
|
C |
- |
2 |
2 |
8 |
|
D |
A |
1 |
1 |
1 |
|
E |
B |
2 |
5 |
14 |
|
F |
C |
2 |
5 |
8 |
|
G |
D, E |
3 |
6 |
15 |
|
H |
F, G |
1 |
2 |
3 |
The expected project completion time is
1
16 days
2
18 days
3
19 days
4
20 days