In two methods A and B of a network analysis, the following methods are true about them.
Method A - Project cost increases if time duration is either increased or decreased.
Method B - Project cost varies directly with time.
Method A and Method B are called respectively
1
Both are PERT
2
PERT, CPM
3
Both are CPM
4
CPM, PERT