The normal cost duration and normal cost of an activity are 10 days and RS. 350/- respectively. the cost slope is Rs. 75/- per day. If the crash duration is 8 days, then what is the crash cost of the activity?

1
Rs. 400
2
Rs. 500
3
Rs. 600
4
None of the above