Which of the following statement(s) is/are true regarding PERT chart in software project management?
I. PERT charts consists of a network of boxes and arrows.
II. In PERT chart, the boxes represent activities and the arrow represents task dependencies.
1
Neither I nor II
2
Only I
3
Only II
4
Both I and II