In a pert activity, optimistic time is 5 hr, pessimistic time is 20 hr and the most likely time is 10 hr then what is the expected time for completion of the activity (in hours)?
1
11.13
2
10.833
3
9
4
10
In a pert activity, optimistic time is 5 hr, pessimistic time is 20 hr and the most likely time is 10 hr then what is the expected time for completion of the activity (in hours)?