Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to the end of the project

Activity

Duration (days)

1-2

2

2-3

1

4-3

3

1-4

3

2-5

3

3-5

2

4-5

4


The critical path (CP) in the network is

1
1-2-3-5
2
1-4-3-5
3
1-2-3-4-5
4
1-4-5