engineering recuitment UKPSC Polytechnic Lecturer Mock Test 2024 Industrial Engineering Operations Research PERT and CPM
Calculate the pessimistic time of the project if a PERT activity is having an optimistic time of 4 days, a mean time of 8 days, and the expected duration of 10 days.
1
12
2
28
3
32
4
24