engineering recuitment UKPSC Polytechnic Lecturer Mock Test 2024 Construction Materials and Management Project Planning
The maximum amount of time that an activity can be delayed without extending the completion time of the overall project is called:
1
Duration
2
Time Limit
3
Float
4
Critical path