Match the List - I (Definition) with the List-II (Suitable notation) and select the most appropriate option.
|
List-I (Definition) |
List-II (Suitable Notation) |
|
A. Subtraction of the addition of earliest start time of current activity and duration of the activity from the earliest start time of successor activity. |
1. Total Float |
|
B. Subtraction of maximum available time and duration of the activity. |
2. Free Float |
|
C. Minimum available time for the activity without delay |
3. Interference Float |
|
D. Difference between Total float and free float |
4. Independent Float |
1
A - 3, B - 4, C - 1, D - 2
2
A - 2, B - 4, C - 1, D - 3
3
A - 2, B - 1, C - 4, D - 3
4
A - 3, B - 1, C - 4, D - 2