engineering recuitment UKPSC Polytechnic Lecturer Mock Test 2024 Construction Materials and Management Project Planning PERT
A PERT activity has an optimistic time of 3 days; pessimistic time of 15 days and the expected time is 7 days. The most likely time of the activity is
1
5 days
2
6 days
3
7 days
4
9 days