A project consisting of five activities needs crashing. The details of crashing that was carried out are given in the table. 

Activity

Normal Time

(days)

Shortest Time

(days)

Cost in Rs. for

Reduction/day

Actually Crashed by(days)

1-2 6 4 100 1 day
1-3 7 5 100 2 days
1-4 10 7 100 1 day
2-4 4 3 200 Not Crashed
3-4 5 4 200 1 day


If the overhead cost of the project is Rs. 200 per day, then the net change in project cost (in Rs.) because of crashing is 

Enter numerical value using the virtual keypad. Round off where necessary.