engineering recuitment AAI JE Technical Mock Test 2020-21 Industrial Engineering Operations Research PERT and CPM
Consider the given project network, where numbers along various activities represent the normal time. The free float on activity 4 – 6 and the project duration, respectively, are
1
2, 13
2
0, 13
3
-2, 13
4
2, 12