Some activities of a project are given in a table with immediate predecessor & duration

Activity

Immediate predecessor

Duration of activity (days)

A

-

12 days

B

A

8

C

A

4

D

A

3

E

B

12

F

C

18

G

C

5

H

E, F

4

I

D, G

9

J

H, I

6

Calculate the shortest project duration time? 