Find the duration of the project from the given table.

Activity

Duration

(days)

Predecessor
A 5 NIL
B 8 A
C 7 A
D 9 C
E 11 B,C
F 3 E
G 4 C
H 3 D,G
I 9 H,F
J 7 H,I

1
28 days
2
39 days
3
32 days
4
43 days