engineering recuitment GATE ME 2023-24 Test Series Industrial Engineering Operations Research PERT and CPM
Given network represents a project:
Three time involved are written on arrows. Calculate the critical path for the network.
1
1 – 2 – 3 – 5 – 7 – 8
2
1 – 2 – 3 – 4 – 6 – 7 – 8
3
Both 1 – 2 – 3 – 5 – 7 – 8 & 1 – 2 – 3 – 4 – 6 – 7 – 8
4
1 – 2 – 3 – 7 – 8