engineering recuitment GATE ME 2023-24 Test Series Industrial Engineering Operations Research Queueing Theory
A warehouse has a loading dock and 3 persons for loading operations. The arrival rate of trucks follows a Poisson distribution with a mean of 4 trucks/hour. The average loading time (by three persons together) per truck is exponentially distributed with a mean of 10 minutes. The charge of the trucks per hour and loading charges per person per hour are Rs.20 and Rs.6, respectively. The total cost (in Rs./hour) is ______.
Enter numerical value using the virtual keypad. Round off where necessary.