A machine shop has received four jobs A, B, C and D for processing on a single CNC machine. All jobs are available for processing on the first day of the production schedule calendar, and processing times and due dates as applicable on the first day are given below. Using earliest due date rule, the average tardiness (in days) is _______. [in integer]

Job

Processing time

(in days)

Due date

(day)

A

8

14

B

5

10

C

7

12

D

9

19

Enter numerical value using the virtual keypad. Round off where necessary.