engineering recuitment GATE ME 2023-24 Test Series Industrial Engineering Operations Research PERT and CPM
PERT calculations yield a project length of 70 weeks with variance of 9 weeks. The number of weeks required to complete project with a probability of 95% is ____ weeks
Probability factor for 95% = 1.647Enter numerical value using the virtual keypad. Round off where necessary.