engineering recuitment GATE ME 2023-24 Test Series Industrial Engineering Production Planning and Inventory Control Aggregate Production Planning and Scheduling
Following jobs are processed on two machines in sequence.
What is the make span time for all the jobs?
|
Job |
A |
B |
C |
D |
E |
F |
G |
|
M1 |
2 |
1 |
2 |
5 |
4 |
3 |
7 |
|
M2 |
3 |
5 |
1 |
9 |
2 |
4 |
6 |
Enter numerical value using the virtual keypad. Round off where necessary.