engineering recuitment GATE ME 2023-24 Test Series Industrial Engineering Production Planning and Inventory Control Material Requirement Planning (MRP)
An order is received for 1000 units of X and already 100 units of X, 50 units of B, 50 units of D and 5 units of C are on hand. The number of C to be order are____
1
22600
2
22595
3
22750
4
22745