engineering recuitment GATE ME 2023-24 Test Series Industrial Engineering Operations Research PERT and CPM
For the network shown in figure, the variance along the critical path is 4.
The probability of completion of the project in 24 days is___
(for Z = 1, p = 84.13 %
Z = 2, p = 97. 72%)
1
68.2%
2
84.1%
3
95.4%
4
97.7%