For the network of activities listed in the project below, which of the following statements are true?

Activity

Time (day)

1-2

3

1-3

2

1-4

6

2-4

5

2-5

7

3-4

2

4-5

4

1
Critical path 1-2-4-5
2
Critical path 1-4-5
3
Expected time = 12 days
4
Expected time = 13 days