engineering recuitment MAHATRANSCO AE Electrical Mock Test Power Systems Economies of Power Generation
What is the reserve capacity, if the maximum demand of generation of power is 50 MW, the load factor of the plant is 60% and the plant capacity factor is 50%?
1
15 MW
2
10 MW
3
20 MW
4
6 MW
5
12 MW