engineering recuitment GATE ME 2023-24 Test Series Industrial Engineering Production Planning and Inventory Control Aggregate Production Planning and Scheduling
A project employed 16 employees and the salary of each employer for one day is Rs. 350. If the aggregate output is Rs. 9000 per day. The labor productivity will be ______(correct up to two decimal places)
Enter numerical value using the virtual keypad. Round off where necessary.