On a typical day, the load on a power plant is as under:

Time

12-5 A.M.

5-9 A.M.

9 A.M. -6 P.M.

6 P.M. – 10 P.M.

10 P.M. – 12 A.M.

Load (MW)

20

40

80

100

20

The installed capacity of plant is 125 MW, the load factor and capacity factor are

1
0.6917, 0.533
2
0.5917, 0.473
3
0.4917, 0.503
4
0.3917, 0.273
5
0.7797, 0.423