Ronit and Hrithik can complete a work in 15 days and 35 days respectively. Hrithik started the work alone and joined by Ronit after the completion of \(\frac{2}{5}\) of the work. Find the time taken to complete the work in this way:

1
22.3 days
2
20.3 days
3
21.3 days
4
19.3 days