engineering recuitment PGCIL Trainee Supervisor Electrical Mock Test 2024 Electrical Machines Transformer Transformer Tests
The primary reason why an open-circuit test is performed on the low-voltage winding of a transformer is that it:
1
draws sufficiently large on-load current for convenient reading
2
involves less core loss
3
needs minimum power input
4
requires least voltage to perform the test