Consider the following scenario: A, B, C, D are processes and X, Y are resources used by the processes.

Process has-X has-Y max-needs-X max-needs-Y
A 35 10 65 40
B 55 80 105 220
C 35 20 110 50
D 0 70 50 90

If Resources available: [X: 40 Y: 40] then what will be a safe sequence so that the processes complete execution without deadlock?

1
ACDB
2
ADCB
3
Both (1) and (2) 
4
ABDC