The yearly load duration curve of a generating station is considered as a straight line from the maximum load of 30 MW to the minimum load of 20 MW. The capacity of the plant is 35 MW. The load factor, plant capacity factor and utilization factor respectively are

1
0.833, 0.714 and 0.557
2
0.833, 0.714 and 0.857
3
0.333, 0.714 and 0.857
4
0.833, 0.314 and 0.857