Which of the following statements are correct?
1. For specialized work open tender is carried out.
2. When the contractor is required to quote his/her rate against each item of work, that is known as percentage rate contract.
1
Only 1
2
Only 2
3
Both 1 and 2
4
Neither 1 nor 2