Pawan can do a piece of work in 32 days. He worked for 8 days and left the work. Thereafter Sandeep finished the remaining work in 27 days. In how many days can Pawan and Sandeep together do the whole work?
1
\(16\frac{16}{17}\) days
2
\(16\frac{13}{17}\) days
3
\(16\frac{15}{17}\) days
4
\(16\frac{14}{17}\) days