In a power station, the maximum demands of six elements of a load as observed from their maximum demand meters are 600W, 510W, 420W, 360W, 100W, 510W respectively. The (coincident) maximum demand of the whole group as observed by the maximum demand meter is only 1000W. The diversity factor is __________ 

1
1.5
2
2.5
3
3.5
4
4.5