engineering recuitment PGCIL Diploma Trainee Mock Test 2024 Estimating, Cost and Valuation Valuation
Consider the following statements:
A. The work costing more than Rs. 2 lakhs is termed as a Major work.
B. The work costing more than Rs. 50000 but not exceeding Rs. 2 lakhs is known as Minor work.
C. The work whose cost does not exceed Rs. 50000 is known as Petty work.
The correct statements are:
1
Both B and C
2
Both A and B
3
Only C
4
All of the above