engineering recuitment HPCL Engineer Mock Test 2024 Power Systems Economies of Power Generation Load Factor
The maximum demand on a plant is 50 kW and load factor is 0.5. find the total energy generated in a year:
1
8.76 × 105 kWh
2
2.19 × 105 kWh
3
3.65 × 105 kWh
4
9.125 × 105 kWh