The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities e and f , respectively, are

Activity

Predecessors

Duration (days)

a

-

2

b

-

4

c

a

2

d

b

3

e

c

2

f

c

4

g

d,e

5

1
0 and 4
2
1 and 4
3
2 and 3
4
3 and 1