engineering recuitment HPCL Engineer Mock Test 2024 Irrigation Engineering Water Requirement of Crops
Find the delta for a crop when its duty is 1728 hectares/cumec on the field, the base period for the crop is 240 days.
1
360 cm
2
240 cm
3
120 cm
4
60 cm