engineering recuitment HPCL Engineer Mock Test 2024 Quantitative Aptitude Time and Work Work Efficiency
P, Q and R can individually do a work in 10, 12 and 15 days respectively. They start working together and P leaves after 2 days. Q left 3 days before completion of work. In how many days was the work completed?
1
6
2
5
3
7
4
8