A can do a piece of work in 98 days, B can do in 147 days and C can do same work alone in 196 days. If on the first day A worked alone and on the second day B and C worked together and on the third day A and C worked together. If they repeat this cycle, then in how many days the total work can be completed? 

1
80(1/3)
2
84(1/3)
3
82(1/3)
4
86(1/3)