engineering recuitment BSPHCL Technician (Electrician) 2024 Mock Test Power Systems Economies of Power Generation Load Factor
If the maximum demand is 100 kW, the load factor is 100%, then find Units generated/annum.
1
876 TWh
2
876 Wh
3
876 kWh
4
876 MWh