engineering recuitment UPSSSC JE Civil 2024 Mock Test Irrigation Engineering Water Requirement of Crops
A canal was designed for a full supply discharge of 60 cumecs. The average supply discharge in the canal is 40 cumecs. The capacity factor of the canal is
1
6.0
2
0.67
3
0.45
4
4.00